C5 Segment 2 and 3A-2
Project Details
SYSTEM
Reinforced Earth MSE Walls
OWNER
Cavitex Infrastructure Corporation
CONTRACTOR
China Road and Bridge Corporation (CRBC)
CONSTRUCTION YEAR
April 2024
DESIGNER + CONSULTANT
- Reinforced Earth Philippines
- DCCD Engineering Corporation
Cavitex is a 14-km expressway running from Roxas Boulevard to Cavite. C5 Segment 2 and 3A-2 is a project facilitated by Cavitex Infrastruction Corporation (CIC).
C5 Segment 2 is a 1.9 km expressway and on the other hand Segment 3A-2 is a 1.6 km stretch. Design, supply, and technical support for the construction of the Reinforced Earth® wall were provided by Reinforced Earth Philippines and designed the walls with Terra Class panels using Geocore® system with high Adherence Geostrap®. The maximum height of the wall in this project was 13 m and an area of 23,900 sqm. Despite the delay in the construction due to a lack of backfill material, the construction finished in April 2024.